Safe work procedures for excavation of swimming pool shells including bulk dig, benching, shaping to design profile, spoil removal, and dewatering operations.
5 work steps
6 hazards identified
6 control measures
5×5 risk matrix
Worker sign-off section
High-Risk Activity Categories
Excavation
Powered Mobile Plant
Legislation Referenced
WHS Reg 2011 r.291 (high risk construction work)
WHS Reg 2011 r.306 (excavation work)
WHS Reg 2011 r.307 (ground conditions — excavation)
WHS Reg 2011 r.214 (management of risks to health and safety)
PPE Requirements
Hard hat (Type 1) (AS/NZS 1801)
Safety footwear (steel cap) (AS/NZS 2210.3)
Safety glasses (AS/NZS 1337.1)
Hi-visibility vest (Class D/N) (AS/NZS 4602.1)
Gloves (task-appropriate) (AS/NZS 2161.1)
Australian Standards Referenced
AS/NZS 1801 — Occupational protective headwear
AS/NZS 2210.3 — Occupational protective footwear
$16.96
$19.95
15% off
Buy This Document
Buy Complete Swimming Pool Construction Pack — Save $34
WHS Reg s.299 Compliant
Editable Word Format
Instant Download
See a sample document →
Also Available As
More JSA Documents for Swimming Pool Construction
$16.96
Buy Now